SUPPLEMENTAL INSTRUCTIONS
Document Name Document Description Issue Date Files
SUPPLEMENTAL INSTRUCTION #1 – Concrete Upstand at West Slab Edge SEPTEMBER 23, 2016 Download
SUPPLEMENTAL INSTRUCTION #2R1 – Elevator Sump Pit Depth October 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #2 – Elevator Sump Pit Depth SEPTEMBER 23, 2016 Download
SUPPLEMENTAL INSTRUCTION #3R1 – Structural Reinforcing for Architectural Feature Walls at Building Entrances October 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #3 – Structural Reinforcing for Architectural Feature Walls at Building Entrances SEPTEMBER 23, 2016 Download
SUPPLEMENTAL INSTRUCTION #4 – Revised Dimensions for Cantilevered Boardroom SEPTEMBER 23, 2016 Download
SUPPLEMENTAL INSTRUCTION #5 R1 – Slab Edge Revisions SEPTEMBER 26, 2016 Download
SUPPLEMENTAL INSTRUCTION #5 – Slab Edge Revisions SEPTEMBER 23, 2016 Download
SUPPLEMENTAL INSTRUCTION #6 – Beam Dimensions SEPTEMBER 28, 2016 Download
SUPPLEMENTAL INSTRUCTION #7 – West Vestibule Entrance Walls and Canopy SEPTEMBER 28, 2016 Download
SUPPLEMENTAL INSTRUCTION #8 – Revisions to ground and 2nd floor partitions/ door schedule. October 17, 2016 Download
SUPPLEMENTAL INSTRUCTION #9 – Rebar revisions to elevator wall between grids B/2 to B/3 October 11, 2016 Download
SUPPLEMENTAL INSTRUCTION #10 – Typical Half Wall/ Millwork Support Detail October 12, 2016 Download
SUPPLEMENTAL INSTRUCTION #11 – 2nd, 3rd, 4th Floor Pour Break at Feature Stair October 11, 2016 Download
SUPPLEMENTAL INSTRUCTION #12 – Re-bar revisions to detail 4/ S-200 at Schoeck connections October 11, 2016 Download
SUPPLEMENTAL INSTRUCTION #13 – Re-routing of 4″ sprinkler main through vestibule parallel to Grid 1; Revised height of interior vestibule framing/ glazing (AGS-1) to suit structure April 12, 2017 Download
SUPPLEMENTAL INSTRUCTION #14 – Modifications to Communication Risers, General Purpose Outlets, Fire Alarm Horn/ Strobe Layout October 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #15 – Clarification of slab edge dimension at Grid A, second floor October 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #16 – Expansion Joint Detail at Bridge Structure, 2nd & 3rd Floors, Grid D. October 26, 2016 Download
SUPPLEMENTAL INSTRUCTION #17 – NOT USED Download
SUPPLEMENTAL INSTRUCTION #18 – Additional Steel Support for cladding fins, four corners of building (3rd, 4th, and roof levels), SSI 011, ASK-25. Revised detailing of soffit panels at underside of 3rd floor level, ASK-20, ASK-21. October 24, 2016 Download
SUPPLEMENTAL INSTRUCTION #19 – Revised mechanical opening behind elevator shaft (Grid E/3) October 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #20 – Additional reinforcing steel required in beams along grid “D” between 2 and 3 at 2nd, 3rd, 4th floors. November 8, 2016 Download
SUPPLEMENTAL INSTRUCTION #21 – Various dimensional clarifications December 7, 2016 Download
SUPPLEMENTAL INSTRUCTION #22 – Additional curtain wall to be installed on the North elevation of the test facility. December 7, 2016 Download
SUPPLEMENTAL INSTRUCTION #23 – Details of water wall in main atrium (Grid C between 2 & 3) December 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #24 – Typical location of water bottle filling stations. December 21, 2016 Download
SUPPLEMENTAL INSTRUCTION #25 R1 – Various dimensional and detail clarifications which are to be incorporated into the Architectural “Construction Update” Drawings, dated 2-Feb-17. February 13, 2017 Download
SUPPLEMENTAL INSTRUCTION #26 – Detailing of retaining wall near Grid 1 between G and J. February 13, 2017 Download
SUPPLEMENTAL INSTRUCTION #27 – Various dimensional and detail clarifications which have been incorporated into the Architectural “Construction Update” Drawings (Issued February 2nd, 2017). February 13, 2017 Download
SUPPLEMENTAL INSTRUCTION #28 – Revisions to curtain wall details. February 13, 2017 Download
SUPPLEMENTAL INSTRUCTION #28R1 – Revisions to curtain wall details. March 22, 2017 Download
SUPPLEMENTAL INSTRUCTION #29 – Revisions to curtain wall/ soffit support steel at U.S. of 3rd floor slab. February 16, 2017 Download
SUPPLEMENTAL INSTRUCTION #30 – Required remedial actions for column at grids C/4 from footing to U.S. second floor. February 16, 2017 Download
SUPPLEMENTAL INSTRUCTION #31 – Additional Walker Duct and Kitchen Revisions for Ground Floor/ Electrical Revisions For Mechanical Equipment February 16, 2017 Download
SUPPLEMENTAL INSTRUCTION #32 – Waterfeature Detail located North of Stair C & Ceiling Detail at Mail Room March 2, 2017 Download
SUPPLEMENTAL INSTRUCTION #33 – Additional HSS Support at Underside of 3rd Floor Midpoint of Grids C and D for Soffit Anchors March 5, 2017 Download
SUPPLEMENTAL INSTRUCTION #34 – Surveyor Layout Drawings March 6, 2017 Download
SUPPLEMENTAL INSTRUCTION #35 – Revised Flooring Finish Plan – Ground Floor Ceramic Tile Layout & Orientation March 7, 2017 Download
SUPPLEMENTAL INSTRUCTION #36 – Floors 2, 3 & 4 Typical Electrical/Mechanical/Sprinkler Elevation Drawings for Coordination March 15, 2017 Download
SUPPLEMENTAL INSTRUCTION #36R2 – Floors 2, 3 & 4 Typical Electrical/Mechanical/Sprinkler Elevation Drawings for Coordination May 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #37 – Floor 4 Layout Revision March 15, 2017 Download
SUPPLEMENTAL INSTRUCTION #37R1 – Floor 4 Layout Revision March 21, 2017 Download
SUPPLEMENTAL INSTRUCTION #38 – Revised Room Finish Schedule Rev05 & associated sketches. March 16, 2017 Download
SUPPLEMENTAL INSTRUCTION #38R1 – Revised Room Finish Schedule Rev05 & associated sketches. March 20, 2017 Download
SUPPLEMENTAL INSTRUCTION #39 – Revised Floor 3 Offices March 16, 2017 Download
SUPPLEMENTAL INSTRUCTION #39 R1 – Revised Floor 3 Offices March 24, 2017 Download
SUPPLEMENTAL INSTRUCTION #40 – Electrical Revisions/Detail. March 21, 2017 Download
SUPPLEMENTAL INSTRUCTION #41 – Detailing of reception desk millwork March 27, 2017 Download
SUPPLEMENTAL INSTRUCTION #42 – Architectural Construction Issue Drawing Update dated April 27th, 2017 with Associated ASK’s May 4, 2017 Download
SUPPLEMENTAL INSTRUCION #43 – Architectural (Partial) Construction Issue Drawing Update – June 5th, 7th & 9th, 2017 and Revised Finish Schedule (Rev. – 06) PART 1 of 3 June 9, 2017 Download
SUPPLEMENTAL INSTRUCION #43 – Architectural (Partial) Construction Issue Drawing Update – June 5th, 7th & 9th, 2017 and Revised Finish Schedule (Rev. – 06) PART 2 of 3 June 9, 2017 Download
SUPPLEMENTAL INSTRUCION #43 – Architectural (Partial) Construction Issue Drawing Update – June 5th, 7th & 9th, 2017 and Revised Finish Schedule (Rev. – 06) PART 3 of 3 June 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #44 – Electrical Modifications to Mechanical Equipment (CCN E-7) and Fire Alarm (CCN E-8) June 15, 2017 Download
SUPPLEMENTAL INSTRUCTION #45 – Deletion of Steel Plate on HSS at 3rd Floor Slab in Level in Atrium June 27, 2017 Download
SUPPLEMENTAL INSTRUCTION #46 – Clarification of Parapet Transition/Retaining Wall Locations at Test Facility June 28, 2017 Download
SUPPLEMENTAL INSTRUCTION #47 R1 – Revised Pocket Size for Training Room Office Partitions July 18, 2017 Download
SUPPLEMENTAL INSTRUCTION #47 – Revised Pocket Size for Training Room Office Partitions July 10, 2017 Download
SUPPLEMENTAL INSTRUCTION #48 – Confirmation of Details & Dimensions of Retaining Walls/Deletion of Sloped Retaining Walls July 14, 2017 Download
SUPPLEMENTAL INSTRUCTION #49 – Addition of Foot Grille, Trench Drain, & Catch Basin at Test Facility July 21, 2017 Download
SUPPLEMENTAL INSTRUCTION #50 – Rename/Re-label Room 422 July 24, 2017 Download
SUPPLEMENTAL INSTRUCTION #51 – Water Fill Stations at GYM 132, and Kitchens 203/303/403 July 31, 2017 Download
SUPPLEMENTAL INSTRUCTION #51 – REV01 – Water Fill Stations at GYM 132, and Kitchens 203/303/403 September 18, 2017 Download
SUPPLEMENTAL INSTRUCTION #52 – Architectual Construction Update – Issued July 28, 2017 August 8, 2017 Download
SUPPLEMENTAL INSTRUCTION #53 – Exterior Site Grading Plan – Update August 23, 2017 Download
SUPPLEMENTAL INSTRUCTION #54 R1 – Operable Office Partition at Ground Floor Training Rooms August 24, 2017 Download
SUPPLEMENTAL INSTRUCTION #55 – Kitchen Equipment Drawings & Specifications August 24, 2017 Download
SUPPLEMENTAL INSTRUCTION #56 – Kitchen Equipment Shop Drawings August 24, 2017 Download
SUPPLEMENTAL INSTRUCTION #57 – Issued for Construction Landscape Drawings & Specifications August 29, 2017 Download
SUPPLEMENTAL INSTRUCTION #58 – KITCHEN CORRIDOR HEIGHTS September 7, 2017 Download
SUPPLEMENTAL INSTRUCTION #59 – JUICE/COFFEE BAR REQUIREMENTS September 20, 2017 Download
SUPPLEMENTAL INSTRUCTION #60 – E/V CHARGER LOCATIONS – REVISED SIDEWALK LAYOUT September 26, 2017 Download
SUPPLEMENTAL INSTRUCTION #60 R1 – E/V CHARGER LOCATIONS – REVISED SIDEWALK LAYOUT September 29, 2017 Download
SUPPLEMENTAL INSTRUCTION #61 – Part 1 of 2 – Millwork Revisions October 4, 2017 Download
SUPPLEMENTAL INSTRUCTION #61 – Part 2 of 2 – Millwork Revisions October 4, 2017 Download
SUPPLEMENTAL INSTRUCTION #62 – Misc. Wall & Door Details October 4, 2017 Download
SUPPLEMENTAL INSTRUCTION #63 – Millwork Countertop Clarifications October 4, 2017 Download
SUPPLEMENTAL INSTRUCTION #64 – Test Facility Lighting & Electrical October 4, 2017 Download
SUPPLEMENTAL INSTRUCTION #65 – Furniture Layouts October 17, 2017 Download
SUPPLEMENTAL INSTRUCTION #65 R1 – Furniture Layouts October 25, 2017 Download
SUPPLEMENTAL INSTRUCTION #66 – Test Facility – Cement Board Layout October 25, 2017 Download
SUPPLEMENTAL INSTRUCTION #67 – Universal Washrooms Wall Tile Layout October 26, 2017 Download
SUPPLEMENTAL INSTRUCTION #68 – Printer Station – Glass Partition Clarification November 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #69 – Stairwells A & B – Tile Layout  November 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #70 – Cafeteria – Ice Machine & Closer Panel  November 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #70 R1 – Cafeteria – Ice Machine & Closer Panel  November 9, 2017 Download
SUPPLEMENTAL INSTRUCTION #71 – Ground Floor – I.T. Area Layout Revision November10, 2017 Download
SUPPLEMENTAL INSTRUCTION #72 – Millwork Drawing A791 – Issued for Construction November14, 2017 Download
SUPPLEMENTAL INSTRUCTION #73 – Revised Floor to Exec Office Layout – 225A & 225B December 1, 2017 Download
SUPPLEMENTAL INSTRUCTION #74 – Hold Open Doors & Revised Door Swing on 4th Lobby December 14, 2017 Download
SUPPLEMENTAL INSTRUCTION #75 – Juice Bar – Increased Clearance December 14, 2017 Download
SUPPLEMENTAL INSTRUCTION #76 – Exit Corridors – Firewall Separation Detail December 14, 2017 Download
SUPPLEMENTAL INSTRUCTION #76 R1 – Exit Corridors – Firewall Separation Detail January 2, 2018 Download
SUPPLEMENTAL INSTRUCTION #77 – Detail Clarification of Glass Guards & Main Vestibules December 15, 2017 Download
SUPPLEMENTAL INSTRUCTION #78 – Lighting at main washrooms 05 & 06 January 17, 2018 Download
SUPPLEMENTAL INSTRUCTION #79 – Kitchen Door D115A January 17, 2018 Download
SUPPLEMENTAL INSTRUCTION #80 R1 – Kitchen/Cafeteria Countertop Extension March 2, 2018 Download
SUPPLEMENTAL INSTRUCTION #81 – 2nd Floor – Addition of Two Work Stations February 23, 2018 Download
SUPPLEMENTAL INSTRUCTION #82 – Revised Site Plan – Depressed Curb February 23, 2018 Download